Travel Disruption A39 and Junction with Timsbury Road – Solar Farm Works

The local authority have asked European Energy Ltd, in the interests of safety and to
minimise traffic disruption, that on the approach to and across the
A39/Top Lane Junction, our contractors extend working hours to include 3
nights from Monday March 25th until Thursday March 28th, between the
hours of 19:00 and 06:00.

The works schedule is now as follows:

1.  Along the A39 from the New Inn Pub, to the Junction between A39 and
Timsbury Road. These works are scheduled to take place from March 11th
to March 27th. Night working 7pm to 6am March 25th to March 28th at the
A39/Top Lane Intersection. Weekend working from March 23rd to March 24th
between 09:00 to 18:00 on Saturday, 10:00 to 18:00 on Sunday.

2.  Closure of Timsbury Road between A39/Timsbury Road Junction, and
Timsbury Road/Priston Lane Junction. These works are scheduled to take
place from April 1st to April 27th.

3.  Closure of Priston Lane between Timsbury Road Junction to entrance of
Castle Farm. These works are scheduled to take place from April 22ndth
to June 7th.

4.  Along Priston Lane between the Timsbury Road Junction up to Castle
Farm under temporary signals. These works are scheduled to take place
from July 8th – August 7th.

European Energy Ltd will do our best to keep disruption to an absolute minimum. If any
issues do arise during the works or you have any concerns, please speak
to the staff on-site, or feel free to contact us directly.